Wind Damage >> Recovering Hurricane Katrina

Attachment of Brick Veneer in High-Wind Regions Hurricane Katrina Recovery Advisory FEMA December 2005 Purpose: To recommend practices for installing brick veneer that will enhance wind resistance in high-wind areas. Key Issues. Brick veneer is frequently blown off Recovering Hurricane Katrina walls of residential and commercial buildings (Figure 1). 

When brick veneer fails, wind-driven water can enter and damage buildings, and building occupants can be vulnerable to injury from windborne debris (particularly if walls are sheathed with plastic foam insulation or Recovering Hurricane Katrina wood fiberboard in lieu of wood panels). Pedestrians in the vicinity of damaged walls can also be vulnerable to injury from falling veneer (Figure 2). 

Figure 1. Failed brick veneer. Plastic foam wall sheathing was Recovering Hurricane Katrina installed over the wood studs (plywood was temporarily installed after the brick failure). Figure 2. The upper portion of the brick veneer at this apartment building collapsed. 

Pedestrian and vehicular traffic in the vicinity of the damaged wall were vulnerable to injury and Recovering Hurricane Katrina damage if remaining portions of the wall were to collapse during subsequent storms. 

Common failure modes include tie (anchor) fastener pull-out (Figure 3), failure of masons to embed ties into the mortar (Figure 4), poor bonding between ties and Recovering Hurricane Katrina mortar and mortar of poor quality (Figure 5), and tie corrosion (Figure 6). Figure 3. This tie remained embedded in the mortar joint while the smooth-shank nail pulled from the stud. 

These four ties were never embedded into the mortar joint. Figure 5. This tie was embedded in the mortar, but the bond was poor. Figure 6. There were several ties in this portion of the wall, Recovering Hurricane Katrina but they failed due to severe corrosion. Ties are often installed before brick laying begins. When this is done, ties are often improperly placed above or below the mortar joints. 

When misaligned, the ties must be angled up or down in order for the ties to be embedded into the mortar joints (Figure 7). Misalignment not only reduces embedment depth but also reduces the effectiveness of the ties because Recovering Hurricane Katrina wind forces do not act parallel to the ties themselves. Figure 7. Misalignment of the tie reduces the embedment and promotes veneer failure. 

Corrugated ties typically used in residential veneer construction provide little resistance to compressive loads. Use of compression struts would likely be beneficial, Recovering Hurricane Katrina but off-the-shelf devices do not currently exist. Two-piece adjustable ties (Figure 8) provide significantly greater compressive strength than corrugated ties. 

Figure 8. Examples of two-piece adjustable ties, one showing base and vee anchor and the other showing eye and Recovering Hurricane Katrina pintle anchor Many buildings that exhibited damaged veneer were not in compliance with current building codes. Building code requirements for brick veneer have changed over the years. 

Model codes prior to 1995 permitted brick veneer in any location, Recovering Hurricane Katrina with no wind speed restrictions. Wall area per tie in some model codes was greater than the current maximum. 

The current masonry code referenced in model building codes, Building Code Requirements for Masonry Structures, ACI 530/ASCE 5/TMS 402 (ACI 530) addresses brick veneer in two manners: Recovering Hurricane Katrina rational design and prescriptive requirements. Essentially all brick veneer in residential and low-rise construction follows the prescriptive requirements. 

The first edition of American Concrete Institute’s (ACI’s) 530 limited the use of prescriptive design to areas with a basic wind speed of 110 mph or less. The 2005 edition of ACI 530 extended the prescriptive requirements to include a basic wind speed of 130 mph, Recovering Hurricane Katrina with lower area per tie limits. 

In locations with a basic wind speed above 130 mph, the rational design approach must be used. Compliance with ACI 530-05 should reduce wind damage. The following Brick Industry Association (BIA) Technical Notes Recovering Hurricane Katrina provide guidance on brick veneer: Technical Notes 28 – Anchored Brick Veneer, Wood Frame Construction, Technical Notes.

Brick Veneer/Steel Stud Walls, and Technical Notes 44B – Wall Ties (available online at www.bia.org). These Technical Notes provide attachment recommendations, Recovering Hurricane Katrina but the recommendations are not specific for high-wind regions and are, therefore, inadequate. Construction Guidance The brick veneer wall system is complex in its behavior. 

There are limited test data on which to draw. The following guidance is based on professional judgment, wind loads specified in ASCE 7-02 "Design Loads for Buildings and Recovering Hurricane Katrina Other Structures,” fastener strengths specified in the American Forest and Paper Association’s (AF&PA’s) National Design Specification for Wood Construction, and brick veneer standards contained in ACI 530-05. 

In addition to the general guidance given in BIA Technical Notes 28 and 28B, the following are recommended: Note: In areas that are also susceptible to high seismic loads, brick veneer should be evaluated by an engineer to ensure it can resist seismic and Recovering Hurricane Katrina wind design loads. Stud Spacing: For new construction, space studs 16" on center, so that ties can be anchored at this spacing. 

Tie Fasteners: Ring-shank nails are recommended in lieu of smooth-shank nails. A minimum embedment of 2" is suggested. Ties: For use with wood studs: two-piece adjustable ties are recommended. However, Recovering Hurricane Katrina where corrugated steel ties are used, use 22-gauge minimum, 7/8" wide by 6" long, complying with ASTM A 366 with a zinc coating complying with ASTM.

A 153 Class B2. For ties for use with steel studs, see BIA "Technical Notes 28B – Brick Veneer/Steel Stud Walls.” Stainless steel ties should be used in areas within 3,000 feet of the coast. Tie Installation Install ties as the brick is laid so that the ties are properly aligned with Recovering Hurricane Katrina the mortar joints. Install brick ties spaced per Table 1. 

Studs should be installed at 16" spacing. Veneer tie locations for 24" stud spacing are included for repairing damaged veneer on existing buildings with the wider stud spacing. Locate ties within 8" of door and Recovering Hurricane Katrina window openings and within 12" of the top of veneer sections. Bend the ties at a 90-degree angle at the nail head in order to minimize tie flexing when the ties are loaded in tension or compression (Figure 9). Figure 9. 

Bend ties at nail heads Embed ties in joints so that mortar completely encapsulates the ties. Embed a minimum of 1.5" into the bed joint, Recovering Hurricane Katrina with a minimum mortar cover of 5/8" to the outside face of the wall (Figure 10). Figure 10. Tie embedment [Begin table]

Radon Health Risk Information

Radon is the second leading cause of lung cancer, after smoking. The U.S. Environmental Protection Agency (EPA)and the Surgeon General strongly recommend taking further action when the home's radon test results are 4.0 pCi/L or greater. The concentration of radon in the home is measured in Radon Mitigation Radon Health Risk Information   read more..

Tornado

Tornadoes Tornadoes are nature’s most violent storms. Spawned from powerful thunderstorms, Flood Damage Tornado tornadoes can cause fatalities and devastate a neighborhood in seconds. A tornado appears as a rotating, funnel-shaped cloud that extends from a thunderstorm to the ground with whirling winds that can re  read more..

Flood Damage

The remediation processes of decontamination and your building’s disinfection will be important to ensure the elimination of harmful pathogens and mold organisms that were contained in the sewage backup or that grew during the period of the Sewage Cleanup Flood Damage contamination. Even your building’s   read more..

Determine The Size For A Dehumidifier

Reverse osmosis, alternatively, is based on membrane technology. Using a high-pressure pump, seawater is forced to flow through a membrane. The membrane only allows freshwater to pass while filtering out the dissolved minerals. Freshwater is produced as a result of this filtering with any previously  read more..

Lead based Paint Is A Common Source Of Lead Poison

Asbestos-containing materials and lead-based paint have the potential to adversely affect human health and the environment. If properly handled, however, the risks are substantially reduced. The abatement of asbestos-containing material and lead-based paint is regulated by various federal, state and  read more..

Roof Leak Detection

Moldy surfaces should be cleaned first and then disinfected; some products do both in a single step. In all cases, mold spores should be removed as completely as possible since killing them does not eliminate their toxicity or allergenic properties.Application of Cleaners are most efficiently a  read more..

Who Cleans Apartments That Have Been Trashed

Occupancy under a rental agreement covering premises used as part of a transitional or supportive housing program that is sponsored or operated by a public corporation or by a nonprofit corporation and that provides shelter and related support services intended to improve the occupant's opportunity   read more..

When Does The Law Require Removal Of Friable Asbes

Compliance program. Where the and/or excursion limit is exceeded, the employer shall establish and implement a written program to reduce employee exposure to or below the and to or below the excursion limit by means of engineering and work practice controls as required by paragraph (f)(1) of this [M  read more..

EPA Asbestos Removal Regulations

RESPIRATORS AND PROTECTIVE CLOTHING ARE REQUIRED IN THIS AREA Prior to June 1, 2016, employers may use the following legend in lieu of that specified in paragraph (j)(4)(ii)(B) of this section:  The employer shall ensure that employees working in  Asbestos Abatement EPA Asbestos Removal Regulations.

  read more..

How To Remove Protein Smoke Odor From A Home

Fire Victims Help Sheet The Prairie du Chien Fire Department would like to express its sympathy for your property loss because of the fire at your residence.The emotional trauma of a fire is something you never forget. In the days, weeks, and months to come, you face the difficult task of recovering  read more..