Wind Damage >> Recovering Hurricane Katrina

Attachment of Brick Veneer in High-Wind Regions Hurricane Katrina Recovery Advisory FEMA December 2005 Purpose: To recommend practices for installing brick veneer that will enhance wind resistance in high-wind areas. Key Issues. Brick veneer is frequently blown off Recovering Hurricane Katrina walls of residential and commercial buildings (Figure 1). 

When brick veneer fails, wind-driven water can enter and damage buildings, and building occupants can be vulnerable to injury from windborne debris (particularly if walls are sheathed with plastic foam insulation or Recovering Hurricane Katrina wood fiberboard in lieu of wood panels). Pedestrians in the vicinity of damaged walls can also be vulnerable to injury from falling veneer (Figure 2). 

Figure 1. Failed brick veneer. Plastic foam wall sheathing was Recovering Hurricane Katrina installed over the wood studs (plywood was temporarily installed after the brick failure). Figure 2. The upper portion of the brick veneer at this apartment building collapsed. 

Pedestrian and vehicular traffic in the vicinity of the damaged wall were vulnerable to injury and Recovering Hurricane Katrina damage if remaining portions of the wall were to collapse during subsequent storms. 

Common failure modes include tie (anchor) fastener pull-out (Figure 3), failure of masons to embed ties into the mortar (Figure 4), poor bonding between ties and Recovering Hurricane Katrina mortar and mortar of poor quality (Figure 5), and tie corrosion (Figure 6). Figure 3. This tie remained embedded in the mortar joint while the smooth-shank nail pulled from the stud. 

These four ties were never embedded into the mortar joint. Figure 5. This tie was embedded in the mortar, but the bond was poor. Figure 6. There were several ties in this portion of the wall, Recovering Hurricane Katrina but they failed due to severe corrosion. Ties are often installed before brick laying begins. When this is done, ties are often improperly placed above or below the mortar joints. 

When misaligned, the ties must be angled up or down in order for the ties to be embedded into the mortar joints (Figure 7). Misalignment not only reduces embedment depth but also reduces the effectiveness of the ties because Recovering Hurricane Katrina wind forces do not act parallel to the ties themselves. Figure 7. Misalignment of the tie reduces the embedment and promotes veneer failure. 

Corrugated ties typically used in residential veneer construction provide little resistance to compressive loads. Use of compression struts would likely be beneficial, Recovering Hurricane Katrina but off-the-shelf devices do not currently exist. Two-piece adjustable ties (Figure 8) provide significantly greater compressive strength than corrugated ties. 

Figure 8. Examples of two-piece adjustable ties, one showing base and vee anchor and the other showing eye and Recovering Hurricane Katrina pintle anchor Many buildings that exhibited damaged veneer were not in compliance with current building codes. Building code requirements for brick veneer have changed over the years. 

Model codes prior to 1995 permitted brick veneer in any location, Recovering Hurricane Katrina with no wind speed restrictions. Wall area per tie in some model codes was greater than the current maximum. 

The current masonry code referenced in model building codes, Building Code Requirements for Masonry Structures, ACI 530/ASCE 5/TMS 402 (ACI 530) addresses brick veneer in two manners: Recovering Hurricane Katrina rational design and prescriptive requirements. Essentially all brick veneer in residential and low-rise construction follows the prescriptive requirements. 

The first edition of American Concrete Institute’s (ACI’s) 530 limited the use of prescriptive design to areas with a basic wind speed of 110 mph or less. The 2005 edition of ACI 530 extended the prescriptive requirements to include a basic wind speed of 130 mph, Recovering Hurricane Katrina with lower area per tie limits. 

In locations with a basic wind speed above 130 mph, the rational design approach must be used. Compliance with ACI 530-05 should reduce wind damage. The following Brick Industry Association (BIA) Technical Notes Recovering Hurricane Katrina provide guidance on brick veneer: Technical Notes 28 – Anchored Brick Veneer, Wood Frame Construction, Technical Notes.

Brick Veneer/Steel Stud Walls, and Technical Notes 44B – Wall Ties (available online at www.bia.org). These Technical Notes provide attachment recommendations, Recovering Hurricane Katrina but the recommendations are not specific for high-wind regions and are, therefore, inadequate. Construction Guidance The brick veneer wall system is complex in its behavior. 

There are limited test data on which to draw. The following guidance is based on professional judgment, wind loads specified in ASCE 7-02 "Design Loads for Buildings and Recovering Hurricane Katrina Other Structures,” fastener strengths specified in the American Forest and Paper Association’s (AF&PA’s) National Design Specification for Wood Construction, and brick veneer standards contained in ACI 530-05. 

In addition to the general guidance given in BIA Technical Notes 28 and 28B, the following are recommended: Note: In areas that are also susceptible to high seismic loads, brick veneer should be evaluated by an engineer to ensure it can resist seismic and Recovering Hurricane Katrina wind design loads. Stud Spacing: For new construction, space studs 16" on center, so that ties can be anchored at this spacing. 

Tie Fasteners: Ring-shank nails are recommended in lieu of smooth-shank nails. A minimum embedment of 2" is suggested. Ties: For use with wood studs: two-piece adjustable ties are recommended. However, Recovering Hurricane Katrina where corrugated steel ties are used, use 22-gauge minimum, 7/8" wide by 6" long, complying with ASTM A 366 with a zinc coating complying with ASTM.

A 153 Class B2. For ties for use with steel studs, see BIA "Technical Notes 28B – Brick Veneer/Steel Stud Walls.” Stainless steel ties should be used in areas within 3,000 feet of the coast. Tie Installation Install ties as the brick is laid so that the ties are properly aligned with Recovering Hurricane Katrina the mortar joints. Install brick ties spaced per Table 1. 

Studs should be installed at 16" spacing. Veneer tie locations for 24" stud spacing are included for repairing damaged veneer on existing buildings with the wider stud spacing. Locate ties within 8" of door and Recovering Hurricane Katrina window openings and within 12" of the top of veneer sections. Bend the ties at a 90-degree angle at the nail head in order to minimize tie flexing when the ties are loaded in tension or compression (Figure 9). Figure 9. 

Bend ties at nail heads Embed ties in joints so that mortar completely encapsulates the ties. Embed a minimum of 1.5" into the bed joint, Recovering Hurricane Katrina with a minimum mortar cover of 5/8" to the outside face of the wall (Figure 10). Figure 10. Tie embedment [Begin table]

Animal Control California

Generally, mountain lions are calm, quiet and elusive. They are most commonly found in areas with plentiful prey and adequate cover. Such conditions exist within Hollister and San Benito County. Mountain lions are an important part of the ecosystem, helping to keep deer and other prey populations in  read more..

How To Get Animals Out Of Your Roof

Compensation would give little incentive to livestock owners to limit losses through improved animal husbandry practices and other management strategies. Not all producers would rely completely on a Animal Damage How To Get Animals Out Of Your Roof compensation program and unregulated lethal control would most likely continue as permitted by s  read more..

How To Pick A Dehumidifier

This unit will be used to illustrate all of Dehumidification How To Pick A Dehumidifier the recuperative precooling and reheating concepts. It will graphically show that they perform the same function—even though some require specific physical arrangements.

 
 HEAT-PIPE RUN-AROUND PRECOO  read more..

How To Choose A Mold Testing Company

Mold remediation, water removal Standing water is a breeding ground for a wide range of micro-organisms and insects, such as mosquitoes. Mosquitoes can spread diseases like West Nile Virus. Micro-organisms, including bacteria and mold, can become airborne and be inhaled. Where floodwater is highly c  read more..

Can Lead Poisoning Be Treated ?

Can lead poisoning be treated? Yes, however, the best approach is to stop your children from coming into contact with lead. The most common way to treat lead poisoning in children is to find the lead source and remove it from their environment. Few children have high enough levels of lead in thei  read more..

How To Clean An Electronic Circuit Board After A F

Collected papers from scientific and technical conferences, symposia, seminars, or other meetings sponsored or cosponsored by NASA. SPECIAL PUBLICATION. Scientific, technical,or historical information from NASA programs,projects, and mission, often concerned with Electronic Restoration How To Clean An Electronic Circuit Board After A F subjects having substantial pub  read more..

Crawl Space Drying

Places that are often or always damp can be hard to maintain completely free of mold. If there's some mold in the shower or elsewhere in the bathroom that seems to reappear, increasing ventilation (running a fan or opening a window) and cleaning more frequently will usually prevent mold from   read more..

Structural Drying Courses

Hurricanes Ivan (2004) and Katrina (2005) have demonstrated that constructing a building to the minimum National Flood Insurance Program (NFIP) requirements or constructing a building outside the SFHA shown on the FIRMs is no guarantee that the building will not be Structural Drying Structural Drying Courses damaged by floodi  read more..

Eliminate Mold And Mildew On Basement Walls

Permitting
 You or your moving contractor will have to obtain permits to move the house on public roads or other rights-of-way. These permits may be required by local governments, highway departments, and Basement Drying Eliminate Mold And Mildew On Basement Walls utility companies, not only in the jurisdiction from which your ho  read more..

Water Damage House Foundation

Cold Weather Tips for Water PipesThursday, November 08, 2012Winter is just around the corner and with freezing temperatures comes the risk of frozen pipes. Here are some suggestions for protecting your home during extremely cold temperatures. Insulate exposed pipes or Water Damage Water Damage House Foundation faucets
  read more..