Question 1: Are we correct that Asbestos Flooring floor tile cleaning activities (normal maintenance such as stripping and buffing operations) are covered under both the Asbestos flooring General Industry Standard (§1910.1001) and the Asbestos flooring Construction Standard (§1926.1101)? 

Answer: Yes. Both standards contain the same requirements for care of Asbestos-containing flooring material. The Asbestos Flooring requirements are at 29 CFR 1910.1001(k)(7) and 29 CFR 1926.1101(l)(3). 

Question 2: Are we correct that for normal cleaning (routine stripping and buffing) that the Asbestos flooring General Industry housekeeping procedures apply, Asbestos Flooring however the Asbestos flooring Construction Standard applies when floor tile clean-up activities are performed as a result of or incidental to a Class I, II or III job? 

Are we also correct, that asbestos flooring floor tile cleaning under the Construction standard is considered a Class IV job? Answer: Stripping or buffing asbestos flooring-containing flooring material previously soiled with asbestos flooring-containing dust or Asbestos Flooring debris from a Class I, II, or III Asbestos Flooring job is not part of the clean-up activity. 

The clean-up activity consists of picking up the debris and vacuuming up the dust. As such, Asbestos Flooring stripping or buffing asbestos flooring-containing flooring material does not come under any of the designated classes of asbestos flooring work defined in the Construction Asbestos flooring Standard. 

The stripping or buffing of asbestos flooring-containing flooring material usually comes under the scope of the General Industry Asbestos flooring Standard. However, stripping or buffing of the flooring material comes under the scope of the Construction Asbestos Flooring Standard if a construction company does it as part of the completion of a construction project. 

Question 3: Both standards discuss stripping operations and [stipulate] that low abrasion pads, wet methods, and Asbestos Flooring speeds lower than 300 rpm must be employed. If higher speed machines are used and current Negative Exposure Assessment (NEA) data exists (by TEM) showing the PEL was not exceeded, is it necessary to submit a written alternative work procedure and/or seek a variance? 

Answer: The Construction Asbestos flooring Standard does not allow the use of alternative procedures Asbestos Flooring for care of asbestos flooring-containing flooring material. The Standard makes allowances for using alternative control methods for only Class I or II asbestos flooring work. 

The fact that the asbestos flooring PELs are not exceeded when the floor stripping uses low abrasion pads at speeds greater than 300 revolutions per minute (rpm) is not a sufficient condition Asbestos Flooring to warrant the receipt of a variance permitting such use. 

In order to receive a variance, Asbestos Flooring the employer must have implemented some means of maintaining asbestos flooring aerosol levels in the employees' breathing zones at levels equal to or less than the levels occurring at speeds lower than 300 rpm. Question 4: While the Construction Standard discusses submitting alternative work procedures, the General Industry Standard does not. 

How does one handle an alternative work procedure regarding the General Industry Standard? Answer: As we noted in our reply to your third question, Asbestos Flooring the Construction Asbestos flooring Standard makes allowances for alternative control methods for only Class I or II asbestos flooring work. 

Therefore, whether the stripping or buffing of asbestos flooring-containing flooring material is covered by the Construction Asbestos flooring Standard or the General Industry Asbestos Flooring Standard, Asbestos Flooring the employer who wishes to use alternative stripping or buffing procedures must seek a permanent variance.

How To File An Insurance Claim For Smoke Damage

EMERGENCY RESPONSE RESOURCES Personal Protective Equipment Respirators Protective Clothing Skin Exposures Eye Protection Hearing Protection Personal protective equipment is very important for any emergency responder. There are five main types of PPE that are covered on this page: respirators and pro  read more..

How To Contract FEMA For Debris Removal

The alternative procedures authorized under the law pertain to debris removal (emergency work)and repair, restoration, and replacement of disaster-damaged public and private non profit facilities(permanent work). This guide outlines the alternative Debris Removal How To Contract FEMA For Debris Removal procedures for debris removal o  read more..

Lead Paint Removal Techniques

The employer selects the initial physician who conducts any medical examination or consultation provided to an employee under this section, the employee may designate a second physician: a. To review any findings, determinations or recommendations of the initial physician; and b. To conduct such exa  read more..

How To Get The Smell Of Raw Sewage Out Of The Hous

The purpose of this publication is twofold: 1. It provides homeowners with basic information on the causes of sanitary sewer backups.2. It provides homeowners with general information on solutions that can be implemented to protect their property from sanitary sewer backups. This Sewage Cleanup How To Get The Smell Of Raw Sewage Out Of The Hous publ  read more..

How To Stop Hoarding Possessions

Pharmacologically, there is little high-quality evidence for benefit of medications. Saxena recently published an open-label study showing positive effects using serotonin reuptake inhibitors (both selective serotonin reuptake inhibitors and serotonin norepinephrine reuptake inhibitors) in OCD and n  read more..

How To Secure A Fenced Perimeter

Hurricane Ike 2008 Ike was a long-lived and major Cape Verde hurricane that caused extensive damage and many deaths across portions of the Caribbean and along the coasts of Texas and Louisiana. It originated from a well-defined tropical wave that moved off the west coast of Africa on August 28 and&n  read more..

Protect Your Home From Radon Gas

Continuously Updated and Available Listings: EPA makes Proficiency Listing information available to states, participants, and others on an ongoing basis. Updated information is available through the Radon Proficiency Program Information Service (RIS) as well as on the Internet (see Section 6.2.  read more..

How To Remove A Heavy Smoke Smell

The official AQI value for particulate matter is derived exclusively from estimated or measured 24-hr average concentrations: this AQI for PM2.5 is reported by the media. PM levels for shorter averaging times in Table 3 are therefore not "official" AQI values, Smoke Damage How To Remove A Heavy Smoke Smell but have been mathematic  read more..

Crime To Operate A Meth Lab

The minimum cleanup requirement includes all steps in Tier 1 Response in addition tothe following: Wash and clean all appliances thoroughly. After cleanup is accomplished, ventilate property for 72 hours. If appropriate,use litmus paper to target areas of potential concern. Alternatively heat a  read more..

Safely Remove Black Mold

 
The more serious health problems have been associated with the toxic black mold, Stachybotrys atra. The mold is greenish-black and slimy, resembling tar or black paint.  read more..